In 2025, we fabricated and installed a 2-hour UL fire-rated glass wall separating the Cubs bullpen batting cages from occupied space at Wrigley Field. Each lite ran north of 600 lbs. We set them by hand on a one-month build. The wall passed UL inspection.
That job is a good lens for everything we know about fire-rated glazing.
What Fire-Rated Glass Is and Isn't
Fire-rated glass is not just thick glass. It's a tested assembly — glass, frame, glazing compound, and anchorage — that must perform as a unit under fire and hose stream tests. The UL or Intertek listing applies to the whole assembly, not just the glass panel.
You can't substitute components. A listed fire-rated glass panel in a non-listed frame fails the inspection. This is the most common mistake we see on jobs that come to us after another contractor walks away.
The Two Numbers You Need to Know
Fire rating — measured in hours (20-minute, 45-minute, 1-hour, 90-minute, 2-hour, 3-hour). This is how long the assembly must contain fire and smoke under the UL 10C test.
Temperature rise — some applications (doors into stairwells, for example) require the assembly to limit heat transfer to the unexposed side. This is where you need products like Pyran Platinum or SuperLite II-XL, not just standard fire-rated glass.
The Wrigley Field application required 2-hour rating, no temperature rise requirement on the glazing (the separation was between a batting cage and a corridor, not an egress path).
Common Chicago Applications
- Stairwell enclosures in commercial buildings (most common)
- Atrium separations in hotels and mixed-use
- Corridor glazing in schools and healthcare
- Tenant separation walls in multi-tenant buildings where the lease line requires rated construction
- Loading dock windows in warehouses
What Drives the Cost
Fire-rated assemblies cost significantly more than standard glazing. The glass itself is more expensive (Pyran, SuperLite, and Contraflam all carry a premium over standard glass). The frames are proprietary rated systems. Fabrication tolerances are tighter. Inspection is required.
For the Wrigley job, the 30-day fabrication-to-install timeline was tight specifically because fire-rated glass is not a stocked item — it's ordered to size from the manufacturer.
How We Approach Fire-Rated Jobs
We read the spec. We confirm the UL listing number. We do not substitute unlisted components. We coordinate the inspection before we leave the site.
If a fire marshal or building inspector has flagged a glazing assembly in your building, call us. We've sorted out a number of situations where the original installer used the wrong product or didn't document the listing properly.
Get a Quote
Chicago Glass Company of Illinois
(708) 800-7120
service@chicagoglasscompany.com
Serving Chicago and the collar counties.
Have a project that needs the right spec?
We've been doing this in Chicagoland since 2016. Tell us what you're working on — quote in one business day.